Day One: Tuesday 27th March 2012
| 08:50 |
Registration, Refreshments and Exhibition
Viewing |
| 09:45 |
Morning Chair
Mike Winter
Chairman of UK Bridges Board |
| 09:50 |
Keynote Address: All we Need to Know about Masonry
Bridges
- Masonry bridges have a long history and a long history of
analysis, over 350 years, but this has been mostly simplistic
- The structures are inevitably complex Even complex analyses are
often based on crude approximations Bridges need to be classified
before they can be analysed
- Asking young engineers to inspect or analyse masonry bridges
without proper training is unprofessional
Bill Harvey
Director, Bill Harvey Associates Ltd
and Visiting Professor, University of Exeter |
| 10:15 |
The Government Perspective
Steve Berry
Head, Highways Maintenance Branch
Department for Transport |
| 10:40 |
Structures Financial Toolkit
Speaker to be announced |
| 11:05 |
Morning Refreshments and Exhibition
Viewing |
| 11:35 |
Bridge Inspector Training and Competence
Project
Stephen Pottle
Structures Manager
Transport for London |
| 12:00 |
Masonry Parapet Assessment
Brian Bell
Network Rail |
| 12:30 |
Audience Question and Answer |
| 12:40 |
Lunch and Exhibition Viewing
|
| 14:00 |
Afternoon Chair
Nick Appleyard
Editor
Surveyor |
| 14:05 |
An Overview of the Olympic Park
Infrastructure
Chris Hendy
Head of Bridge Design and Technology
Atkins
David Baird
Olympic Development Agency |
| 14:30 |
National Bridge Stock Condition
Kevin Dentith
Principal Engineer, Bridge Maintenance
Devon County Council |
| 14:55 |
Case Study: Salford Quays -Media City
Footbridge
Peter Curran
Director
Ramboll UK Ltd
|
| 15:20 |
Afternoon Refreshments and Exhibition
Viewing |
| 15:50 |
Risk Based Allocation of Maintenance
Spend
Sharan Gill
Structures Engineer
TFL |
| 16:15 |
Case Study: The Mersey Gateway - A Bridge to
Prosperity
- An overview of the project outlining the need for the
crossing
- The expected benefits T
- The civil engineering challenges; form and reasoning of the
"reference" design; and the procurement process.
Ian Draycott
Highway Authority Liaison Engineer
Mersey Gateway Project |
| 16:40 |
Audience Question and Answer |
| 16:50 |
Chair's Summary and Close of Day One
|
| 17:00 |
Bridges 2012: Home & Away Networking Drinks
Reception |
Day Two: Wednesday 28th March 2012
| 08:50 |
Registration, Refreshments and Exhibition
Viewing |
| 09:45 |
Morning Chair
Helena Russell
Editor
Bridge Design and Engineering |
| 09:50 |
Forth Replacement Crossing - Specimen Design and
Procurement Approach
- Background to the project
- Design Criteria including Eurocodes, Ship Impact, Wind
Climate
- Development of the Specimen Design
- Approach to writing the Employer's Requirements
Steve Kite
Associate Director, Bridges
Arup |
| 10:15 |
Forth Replacement Crossing - Winning Tender Design and
Planning for Construction
- Design options for optimal economical delivery
- Construction sequence and programme
- Construction methods
Carson Carney
Manager-Cable Stay Bridge Superstructure
American Bridge |
| 10:40 |
Design & Construction of the Vidin-Calafat Bridge
over the Danube River, Bulgaria- Romania
Vardaman Jones
Director, Project Delivery
High-Point Rendel
|
| 11:05 |
Morning Refreshments and Exhibition
Viewing |
| 11:35 |
New Materials Technology for Small and Medium-Span
Bridges - Learning from the North American Lead
Dr. Lee Canning
Principal Engineer
FRP Bridges - Recent Developments and Opportunities
|
| 12:00 |
Cable Preservation and Monitoring Techniques - the
Latest State of the Art
Charles Cocksedge
Technical Director, Transportation
Aecom
|
| 12:25 |
Audience Question and Answer |
| 12:35 |
Lunch and Exhibition Viewing |
| 14:00 |
Afternoon Chair |
| 14:05 |
Bridge Design Competitions - Avoiding the
Pitfalls?
- Can design contests retain their relevance in a recession?
- Examples of bridge competitions which have failed
- Examples of bridge competitions which have worked well
- The new best practice guidelines for bridge design competitions
from IABSE
Brian Duguid
Associate
Mott MacDonald |
| 14:30 |
Integral Design of Footbridges in the
Benelux
Laurent Ney
CEO
Ney & Partners
|
| 14:55 |
Afternoon Refreshments and Exhibition
Viewing |
| 15:25 |
Footbridge Monitoring Project - Update on Progress so
Far
Elena Barton
Research Scientist
National Physical Laboratory |
| 15:50 |
Derry Peace Bridge Case Study
- Design team response to client's aspirations for a "living
landmark and lasting legacy".
- Visual Concept of Bridge - how the bridge is uniquely designed
to suit its specific context.
- Structural Concept of the Bridge
- Fabrication and Erection of the Bridge
James Marks
Associate
Wilkinson Eyre Architects
with Kandiah Kuhendran, AECOM & Philip Brown, Graham
Construction
|
| 16:15 |
Audience Question and Answer |
| 16:30 |
Chair's Closing Remarks and Close of
Conference |